Construction
Institute of Plant and Microbial Biology

icon
|  HOME  |  SITEMAP  |
icon

Construction of the Agricultural Technology Building

IMAGE IMAGE IMAGE

December 22, 2006 marked the start of construction for the new Agricultural Technology Building. When completed at the end of 2008, the new building will contain sixteen new laboratories for IPMB and the Agricultural Biotechnology Research Center. Our core facilities for bioinformatics, proteomics and metabolomics and cell biology will also relocate to the new building. This new building is adjacent to our present building and will be connected to it on several floors to allow easy movement between our present facility and the new building. This state-of-the-art facility will be a welcome enhancement to our research space.

Below are some snapshots of the construction progress. Please continue to check this site for future progress reports.

image
2006-11-15
The building site is fenced off to prepare for the start of construction.

image02
2006-11-20
Groundbreaking Ceremony. Officials from IPMB and ABRC mark the end of the long planning process and official start of construction. In accordance with Chinese custom, an auspicious date is chosen and ceremonial offerings made to ensure smooth progress of the construction.

image02
2006-12-29
Site preparation is in progress and materials arrive to begin work on the new buildingˇ¦s two basement levels.

image04
2007-1-5
Concrete is poured as work continues on the two basement levels. The Genomics Research Center can be seen in the background.

image04
2007-1-12
Work continues on the two basement levels. The present IPMB building can be seen in the background.

image04
2007-2-6
Structural steel is lowered into position to form the basement walls.

image04
2007-2-26
Work continues on the two basement levels. The present IPMB building can be seen in the background..

image04
2007-7-19
The basement levels have been excavated and steel put into place in preparation for pouring the first floor and above ground walls.

image04
2007-7-19
Part of the ground floor, including the beginning of the buildingˇ¦s auditorium are complete.

image04
2007-7-23
The above ground steel and concrete superstructure rises quickly toward the final height of seven above-ground floors.

image04
2007-12-13
The ˇ§Main Beam Installation Ceromonyˇ¨ (ie. ˇ§Topping Out Ceromonyˇ¨) is held as the above ground superstructure is nearly complete.

image04
2007-12-13
Academia Sinica President Chi-Huey Wong attends to topping out ceromony along with IPMB director Ho and associate directors Long-fan Oliver Chen and Na-sheng Lin. An auspicious date is again chosen and ceremonial offerings made to ask for continued good progress in the contruction.

image04
2008-01-20
The main structure of the building is complete and the first stage of interior work is beginning.

Page | 1 | 2 | 3 |
 

 Institute of Plant and Microbial Biology, Academia Sinica, Taipei, Taiwan, Republic of China
Tel: 886-2-27899590  Fax: 886-2-27827954

Updated: 10/19/2007